Real Case: 100kWh Energy Storage System for a Cold Storage Warehouse

Real Case: 100kWh Energy Storage System for a Cold Storage Warehouse

1. Introduction: Why Cold Storage Needs ESS

Cold storage warehouses operate under strict temperature control, often 24/7, making them highly energy-intensive. With rising electricity costs and grid instability in many regions, energy storage systems (ESS) are becoming a vital solution for:

  • Reducing peak demand charges
  • Ensuring backup power during outages
  • Supporting onsite PV generation
  • Stabilizing internal loads

In this case study, we walk through a real-world 100kWh ESS project implemented for a cold storage facility, highlighting design logic, product choices, and key lessons learned.


2. Project Background

🔹 Client Profile

  • Industry: Frozen food distribution
  • Location: Southeast Asia
  • Load Type: 60 kW baseline with 80 kW peak during defrost cycles
  • Power Supply: Grid + rooftop PV (50 kWp)
  • Pain Points:
    • High peak demand charges
    • Intermittent power outages
    • Grid voltage fluctuation affecting compressors

3. Design Objectives

The client wanted a solution that would:

✅ Store solar energy for evening use
✅ Support load shifting and peak shaving
✅ Provide at least 2 hours of backup for essential loads
✅ Automatically switch to battery during blackouts
✅ Be modular and easy to maintain


4. System Configuration Overview

📦 ESS Size: 100 kWh usable capacity

🔋 Battery Type: LFP (LiFePO₄), 51.2V modular packs

Inverter Type: 3-phase 100 kW hybrid inverter (with grid + PV input)

☀️ PV Integration: 50 kWp rooftop solar, 3 MPPT inputs

🧠 EMS Integration: Intelligent energy management system with cloud monitoring

🔁 Operating Mode:

  • Self-consumption (solar first)
  • Peak shaving (grid + battery blending during peak)
  • Backup (auto switch within 20 ms)

5. Component Selection and Sourcing Logic

ComponentModel / SpecSourcing Note
Battery Modules51.2V, 100Ah LFP (20 units)High cycle life, rack-mountable
Inverter100 kW hybrid, 3P 400V ACSupports PV + grid + battery input
PV System50 kWp (monocrystalline panels)Matched with inverter MPPT voltage range
BMSIntegrated with CAN/RS485Communicates with inverter and EMS
EMSCloud-connected, programmable logicEnables load profile adjustment

Vendor Selection Focus:

  • Compatibility (inverter–battery–BMS protocols)
  • After-sales support & remote diagnostics
  • Ability to ship in 40’ container with all accessories

6. Load Profile and System Sizing

🧊 Cold Storage Load Curve (24h)

TimeTypical Load (kW)Notes
00:00–06:0035–40 kWSteady cooling
06:00–09:0050–60 kWLoading operations + door opening
12:00–14:0070–80 kWDefrost cycles + peak ambient temp
18:00–22:0060–65 kWLoading + packaging

📐 Sizing Logic

  • 100 kWh usable capacity provides:
    • ~1.5 hours at peak (65 kW)
    • 2.5 hours for essential loads (40 kW)
  • Battery oversizing (15%) included for long-term degradation buffer
  • System set to limit grid draw to 50 kW during 80 kW peak with 30 kW battery boost

7. Installation Highlights

🏗 Logistics & Deployment

  • Delivery: All components pre-packaged for container shipment
  • Onsite install: 5 days with 3 technicians
  • Control cabinet pre-wired with inverter, ATS, EMS controller
  • Battery racks mounted in adjacent climate-controlled room

🧪 Commissioning & Tests

  • Load simulation using dummy load bank
  • PV inverter MPPT calibration to match actual site voltage
  • EMS logic tested for blackout and recovery scenarios
  • Thermal imaging used to verify battery temperature profiles under load

8. Performance Results (After 3 Months)

MetricResult
Average Peak Reduction~25 kW shaved from grid
Monthly Savings (demand charge)~$1,200 USD/month
Solar Self-Consumption Rate85–90%
Battery SOC usage per day60–80 kWh cycled
Outage Backup Response< 30 ms, seamless transition

🔧 Maintenance calls: Zero
📈 Client satisfaction: High – expanding to second site


9. Lessons Learned & Best Practices

✅ What Worked Well

  • Use of LFP batteries avoided temperature concerns in tropical climate
  • Hybrid inverter with 3 MPPT allowed optimal solar capture
  • Modular racks simplified transport and space layout
  • EMS enabled future remote tuning of load schedules

⚠️ What to Watch Out For

  • PV panel cleaning is critical due to dust and humidity
  • Battery room temperature must be controlled even with LFP
  • Integrator must test BMS–inverter compatibility before shipping
  • Plan for battery expansion by allocating space and ports in advance

10. Takeaways for Foreign Trade Partners

For export-oriented partners or energy solution providers:

  • Cold storage is a prime sector for small-to-mid scale ESS
  • Focus on hybrid inverter + LFP battery bundles with proven interoperability
  • Offer pre-configured systems with manuals, SLDs, and remote support
  • Include options for EMS or PLC integration with user-friendly dashboards

🧠 This project proves that even a 100 kWh system, when designed with precision, can deliver strong ROI and client trust in C&I storage applications.


相关文章

开始在上面输入您的搜索词,然后按回车进行搜索。按ESC取消。